On a period refurbishment, the windows are often priced as straight replacements before anyone has opened one. Original sashes that stick, rattle and shed paint look like the weakest part of the building.
They are also the element where consent, Building Regulations and programme all change depending on whether you repair or replace. A short survey before the specification is fixed stops you pricing work the building does not need, or work the planning authority will not allow.

Start With the Consent Position
Establish what the building’s status allows before the window package is priced. The answer depends on whether it is a house, a flat or a listed building.
- Houses. The Planning Portal says planning permission is usually not needed for repairs, maintenance, or new windows that match the originals. Internal secondary glazing is treated the same way.
- Article 4 Directions. A council can withdraw those permitted development rights for a street or area. This is often done in conservation areas.
- Flats and maisonettes. The permitted development allowances apply to houses, not to flats and maisonettes. A terrace converted into flats needs a different check from the house next door.
- Listed buildings. Listed building consent is needed for any significant works, internal or external.
Leaseholders may also need permission from their landlord or management company. Confirm the position with the local planning authority in writing before pricing; a client’s recollection is not evidence.
Know When Building Regulations Apply
Repair and replacement follow different compliance routes. Building Regulations have applied to all replacement glazing since 1 April 2002, and an external window is a “controlled fitting”, as the Planning Portal explains.
Its guidance for houses draws the line as follows:
- The regulations normally apply when the whole fixed frame and opening parts are replaced.
- They do not normally apply when the work is no more than replacing broken glass, rotten sashes or rotten sections of the main frame.
Where windows are replaced, an installer registered with a competent person scheme can certify the work and issue a certificate. Otherwise, the work needs approval from building control, which issues a certificate of compliance. Keep that paperwork in the handover file, because the owner may be asked for it when the property is sold.
Thermal performance is not the only test. The guidance also covers ventilation, means of escape and safety glazing in critical locations, such as glazing within 800mm of floor level. A replacement window should give at least the same potential for escape as the one it replaces.
Listed dwellings and dwellings in conservation areas are treated differently on energy efficiency. Approved Document L, Volume 1 (2021 edition with 2023 amendments) says work need not comply fully where that would unacceptably alter the dwelling’s character or appearance. It must still comply as far as is reasonably practicable. A 2026 edition has also been published, so agree with building control which edition applies to your project.
Survey the Windows Before Pricing
Survey every window individually and schedule it as repair, repair with upgrade, or replace. A mixed schedule is normal on a period building.
Check each window for:
- Sill and bottom rail. Probe for soft timber where water sits.
- Box frame. Check the pulley stiles and outer linings for decay and movement.
- Sash joints. Look for open joints at the corners and at the meeting rail.
- Cords, pulleys and weights. Note broken cords and seized pulleys.
- Operation. Confirm both sashes move. Top sashes are often painted shut.
- Glass and putty. Record any old, uneven glass worth keeping and any failed putty.
- Gaps. Note rattles and visible daylight around the sashes.
Historic England’s guidance on traditional windows says they can often be repaired simply and economically, usually for less than replacement. Decayed sections can be cut out and new timber spliced in, with cords, beads and putty renewed at the same time. A specialist in sash window repair and restoration will normally price this window by window.
Upgrade Options That Keep the Original Window
A repaired sash window can be upgraded without replacing it. Research commissioned by English Heritage, now Historic England, at Glasgow Caledonian University tested an 1880s sliding sash window.
- Draught-proofing cut air infiltration through the window by as much as 86%.
- Secondary glazing with a low-emissivity coating cut heat loss through the window by around 60%.
Secondary glazing sits inside the room, so the external appearance is unchanged. Check the consent position first on a listed building.
Where a window is beyond repair, or the client wants double glazing within the sash itself, double-glazed timber sash windows can be made to match the original pattern. That is a replacement, so the planning and Building Regulations checks above apply in full.
Protect and Sequence the Work
Original joinery needs protecting from the rest of the job. Three points belong in the programme and the method statement.
- Assume old paint contains lead. Lead was used in some paints for windows, doors and other woodwork until the mid-1960s, as Cambridge City Council’s guidance explains. Avoid dry sanding and burning off, and plan the work under the Control of Lead at Work Regulations 2002.
- Protect retained windows. Board or sheet them before strip-out and wet trades, and agree scaffold tie positions so frames and sashes are not damaged.
- Sequence the overhaul. Programme window repairs after the dirty trades and before final decoration. Bespoke replacements are made to order, so place that order as soon as the schedule and consents are settled.
Commercial and Mixed-Use Buildings
The same checks apply to offices, shops and converted period buildings, with two differences. The work usually happens around occupiers, and there are often many near-identical windows.
Survey every window before ordering, even where they look the same from the street. Agree working hours, access and temporary security with the building manager at tender stage. Contractors used to sash windows in commercial buildings can phase the work floor by floor so the premises stay in use.
Before You Specify: A Short Checklist
- Confirm house, flat or listed status, and any Article 4 Direction, with the planning authority.
- Decide from a window-by-window survey which windows are repaired and which are replaced.
- Agree the Building Regulations route and certification for any replacements.
- Price draught-proofing and secondary glazing before full replacement.
- Put lead-safe working, protection and replacement lead times in the programme.