Solid Wall Insulation by the Book: Four Stages, and the Shortcut Waiting at Each One

I started in insulation at 19, surveying homes for the CERT scheme, and went on to work as a domestic energy assessor, producing EPCs for other installers. These days I run Insulation Installers Scotland, a Glasgow installer with PAS 2030 accreditation and TrustMark registration, and solid walls are the part of our work where the paperwork carries the most weight.

Under PAS 2035, a solid wall job sits on one of the higher-risk paths, B or C, which brings more assessment and a full design stage. Like every funded PAS 2035 job, it also has a retrofit coordinator, who has to sign off the moisture risk before anyone fixes a frame to a wall. The National Audit Office’s October 2025 report on the Energy Company Obligation shows the price of skipping steps: 38 businesses suspended, 21 of them reinstated by September 2025, and around 2,900 homes put right by that point, out of more than 30,000 homes with major issues.

The job breaks into four stages. Each one has a familiar shortcut, and a client or main contractor can catch most of them from the paperwork.

The Assessment, and the Version Done From a Desk

A retrofit assessment is the foundation of the file. The assessor records the house as it stands, its energy performance and its condition, including the defects that need fixing before insulation goes anywhere near a wall. On a solid wall those defects decide the job. A blocked gutter soaking one corner, or a patch of damp behind a wardrobe, needs fixing first, or the insulation seals the problem in.

The shortcut is an assessment that reads like an EPC with a new cover sheet. It has the floor area and the boiler model and says nothing about the gutters. Ask to see the condition section. If it runs to two lines, the design built on top of it is guesswork.

Design Starts With the Moisture Question

The designer’s first decision on a solid wall is how the wall will dry once it has insulation on it. If the wall is brick, and either rendered or low-absorption, the designer can go vapour-closed: hemp on a timber frame, a Pro Clima Intello Plus membrane on the warm side, then plasterboard and skim. Sandstone takes the opposite route, a vapour-open internal wall insulation build-up in which every layer from the lime parge out to the finish plaster lets moisture leave the stone.

A person in a black hooded jumper applies solid wall insulation to a stone wall in a room undergoing renovation.

We back those choices with a library of build-ups validated in WUFI hygrothermal software for the Scottish wall types we see, and we choose the entry for a given wall from the survey. The shortcut at this stage is one specification for every wall in the house: foil-backed PIR board dot-and-dabbed onto sandstone, because it goes up fast and the van already carries it. It looks fine on handover day. The trouble builds inside the wall, where no inspection reaches.

Installation: The Layers and the Edges

On sandstone, our build-up goes on in a fixed order. The crew strips the wall back to stone and applies a lime parge coat. Next come two 50mm IndiTherm hemp batts compressed into a 45mm timber frame, followed by a 15mm wood wool board as the plaster carrier and two coats of lime plaster with mesh in the base coat. Our six employed installers fit the insulation, and the same trusted lime plasterer finishes our jobs.

The shortcuts here sit at the edges. A crew that boards over old gypsum plaster instead of stripping to stone leaves a layer behind the new system that the design did not allow for. Leave the window reveals bare and they become the coldest surface in the room, which is where the mould starts. Lime needs more preparation than gypsum and the programme stretches with it, so a crew running behind is tempted to rush the coats or drop the mesh. The cracks show up once the heating goes on.

Wall studs partially covered with grey soundproofing insulation panels secured by plastic fasteners during the insulation installation process.

Handover: The File Outlives the Crew

A compliant job ends with paperwork someone can still use in ten years. The coordinator signs the job off, we lodge the measure with TrustMark, and the client receives a handover pack with the design and photographs of each stage. Our jobs carry a 25-year workmanship guarantee.

The pack should also cover decoration. A vapour-open wall needs a finish paint that lets vapour through, and a decorator who rolls a vinyl emulsion over fresh lime plaster puts a low-permeability skin on the face the wall is meant to dry through. We give clients paint guidance at handover for that reason, because the decorator arrives after we have gone.

The shortcut is a guarantee with no file behind it. If the installer cannot show you the design and the photographs, you have nothing to measure the work against on the day you need to call the guarantee in.

A Word on Coordinators

The coordinator holds the chain together, and in Scotland qualified PAS 2035 coordinators are in short supply. We bring in qualified coordinators from outside the company for funded work. A contractor who quotes a start date next week on a funded solid wall job should be able to tell you who has signed off the risk assessment, and put that name in writing.

By Calum Farquhar, director, Insulation Installers Scotland.