The Tender Said “BIM Level 2” and Nobody in the Office Knew What That Meant

For most of its twenty-two years, our joinery and fit-out business in the West Midlands ran on two things: good craftsmen and a very experienced draughtsman called Graham, who had been producing our shop drawings in AutoCAD since before some of our apprentices were born. We did reception desks, wall panelling, bespoke storage and the occasional full office fit-out, mostly for main contractors we’d worked with for years. The drawings went out as PDFs, got marked up in red pen, came back, and Graham revised them. It worked.

Then, two springs ago, we won a package on a new university teaching building in Coventry. Around £400,000 of joinery, the biggest single job we’d ever priced. The tender documents ran to a couple of hundred pages, and somewhere in the middle was a clause saying all trade packages had to deliver information in line with ISO 19650 and the client’s BIM Execution Plan, including a federated model with our elements modelled to a stated level of information. Our contracts manager read it out in the Monday meeting and there was a long silence. Graham said, very calmly, that he didn’t do Revit.

What the Client Actually Wanted

It took us a few phone calls with the main contractor’s information manager to understand what was being asked. They didn’t just want our drawings. They wanted every bit of fixed joinery, the reception counter, the wall linings, the fitted benching in the labs, the acoustic panels, modelled as proper objects in Revit, with the right parameters attached: material, fire rating, manufacturer, maintenance information. Those objects would sit in the federated model alongside the structure, the services and everyone else’s work, and they’d be used for clash detection before anything was built and for facilities management after handover.

That last part was the eye-opener. The university’s estates team wanted to be able to click on a lab bench in the model in five years’ time and see what laminate it was finished in and who to call about replacing a hinge. Our nicely detailed AutoCAD drawings simply couldn’t do that.

Deciding How to Cope

We looked at three options. The first was to train Graham and one of the younger lads in Revit and buy the licences. That was the long-term answer, but the model was due in eight weeks, and nobody learns Revit to a federated-model standard in eight weeks while also running a workshop. The second was to hire a BIM technician. We tried, briefly, and discovered that every decent one in the region was already working for a main contractor or a big consultancy, at salaries that didn’t fit a firm of our size.

The third was to bring in outside help for the first job and learn alongside them. A friend who runs a shopfitting firm near Leicester had been through the same thing and put us in touch with a drafting studio that offers Revit BIM services to trade contractors and manufacturers. We sent them Graham’s AutoCAD shop drawings, the client’s BIM Execution Plan, the parameter list and the main contractor’s model template, and had a long call to agree who would do what.

How the Work Actually Went

What surprised me most was how much of Graham’s knowledge carried straight across. The studio built our elements as Revit families, but every dimension, every joint and every fixing detail came from his drawings, and when the modellers had a question about how a counter return was actually built, they asked him rather than guessing. He went from being worried about being left behind to being the person everyone checked with.

The first clash detection run was humbling. The model showed our wall linings in two lecture theatres clashing with a run of sprinkler pipework that had moved since our drawings were done, and a lab bench sitting forty millimetres into a riser. On a traditional job we’d have found both on site, with a fitter standing there holding a panel that didn’t fit. Here, we found them on a screen in week five and sorted them in a coordination meeting. The main contractor’s project manager told me afterwards that our package had produced fewer site queries than any other trade on the job, which, for a firm that had never touched BIM, felt like a small miracle.

The Parts That Were Harder Than Expected

It wasn’t all smooth. The parameter requirements were fiddly, and we underestimated how long it would take to gather manufacturer data for every hinge, edging and laminate. Our suppliers weren’t used to being asked for product data sheets in specific formats, and a couple of them took weeks to respond. The file naming and model exchange protocol in the BIM Execution Plan also caught us out early on, when two of our first submissions were rejected purely because the files were named wrongly.

The cost was real, too. The outside modelling added a little over two per cent to our package price. We’d priced some of it, but not all, because we didn’t really understand the scope at tender stage. Next time we’ll price it properly.

What We Did Afterwards

We’ve now delivered three BIM jobs. On the second, Graham and our youngest draughtsman, who had done a Revit course at college, worked alongside the studio and built some of the simpler families themselves. On the third, we did most of the modelling in-house and used the studio for the complicated pieces and for checking our models against the client’s requirements before submission. We now have our own library of Revit families for our standard products, which has started to win us work on its own, because a main contractor can drop our reception desks and storage walls straight into a model at tender stage.

If you run a joinery, shopfitting or fit-out business and the words ISO 19650 have just turned up in a tender, my advice is not to panic and not to try to do it all yourself overnight. Read the BIM Execution Plan carefully, ask the information manager every question you have, price the modelling properly and get help for the first job while your own people learn. The craftsmanship is still the hard part. The model is just a new way of showing it.