Two quotations for replacement timber casement windows can look similar while covering quite different work. One may include new outer frames, factory finishing and internal decoration. Another may leave some of those items for the main contractor or property owner to arrange. Once a survey has confirmed that replacement is needed, a written specification allows suppliers to price the same work.
On a refurbishment project, the quotation needs to establish who will supply the windows, who will fit them and who will make good the surrounding finishes. For a period property, it must also establish how the new windows will match the building’s existing detailing.
Define the replacement and agree the design
Start with a window schedule identifying each unit by room and position. Record its dimensions, which sections open and the direction in which they open. A casement is hinged, unlike a sliding sash window. Check the hinge positions and allow enough clearance for each opening casement. Confirm who will take responsibility for the final survey dimensions before manufacture.
The quotation should state whether it covers complete window units, including the outer frames and cills, or new opening casements fitted into retained frames. If any existing timber will remain, have the supplier record its condition and the preparation needed before installation.
When commissioning bespoke units from Repair A Sash, a timber casement window specialist in London, request drawings showing the proposed layout, frame profiles and glazing bars. In a period building, changes to these details can alter the appearance even when the overall opening stays the same size. Agree whether the casements will sit flush with the frame or overlap it. Where suitable original windows survive elsewhere in the building, use them as a reference.
Resolve permissions before placing the manufacturing order. For a property in England, check listed status, conservation-area controls and any Article 4 direction with the local planning authority. On a leasehold property, check the lease and obtain any required freeholder consent. Record the approved design in the order documents.
Specify the timber and frame construction
A quotation describing the material simply as “hardwood” or “softwood” leaves an important part of the specification open. Ask for the timber name and whether the frame and opening casements use solid or engineered sections.
Options include engineered Redwood, Red Grandis and Accoya. Engineered Redwood provides a softwood option for painted joinery. Red Grandis is a hardwood, while Accoya is wood modified through acetylation to improve dimensional stability and durability.
Ask the manufacturer to explain the proposed choice for the property’s exposure to the weather and the intended finish. Where engineered sections are specified, confirm that they are intended for external window joinery. Record the material in the accepted quotation so that any proposed substitution requires agreement before manufacture.
Specify the glazing and window performance
“Double glazed” is not a complete specification. Ask for the glazing build-up, overall unit thickness and the declared thermal performance of the complete window. A centre-pane U-value describes the glass alone. The whole-window U-value also accounts for the frame and the edge of the glazing; lower U-values indicate less heat transfer.
For period properties, discuss whether conventional double glazing, slimline units or vacuum glazing are compatible with the proposed frame design and any consent conditions. Request a sample or section drawing so that frame widths and glazing bars can be checked before production.
Have the installer identify where safety glazing is required and include it in the quoted specification. For a property on a busy road, ask for acoustic test data for the proposed window and discuss how ventilators will affect its performance.
If improving the EPC rating is part of the project, have the proposed changes assessed for that property before relying on a particular outcome.
Plan ventilation and safe operation together
Include ventilation in the survey and quotation. Because replacement windows can reduce draughts, the installer should check how background ventilation will be maintained and specify any changes needed.
For work in England, the government’s Approved Document F frequently asked questions explain that a window locked slightly ajar on a night latch is not an appropriate background-ventilation solution. Agree the location and appearance of any required ventilators before manufacture, particularly where heritage details or street noise need consideration.
List the hinges, handles and locks, including their finish. Confirm how the windows will be operated and cleaned, particularly on upper floors. Where restrictors are proposed, have the installer confirm their suitability for the occupants. The installer should also record the required clear opening for any escape window and confirm that the fittings allow it to open as required.
Agree the finish before manufacture
State the internal and external colours, the coating system and how much finishing will be completed in the factory. “Primed” and “fully finished” describe different stages of work. Confirm who will apply any remaining coats and repair damage caused during fitting. Include the cost of this work in the quotation or the wider refurbishment budget.
Ask for the coating manufacturer’s care instructions and any restrictions on colour choice. Request written details of inspection and recoating requirements for the proposed finish and exposure.
The timber, coatings, sealed glass units and installation may each have different guarantee terms. Check what each guarantee covers and which maintenance records the owner will need to keep.
Make the installation quotation complete
Give each contractor the agreed window schedule and request an itemised quotation. Alongside manufacture and fitting, it should identify:
- Access equipment, scaffolding and protection for occupied rooms.
- Removal and disposal of the existing windows.
- Work to cills, reveals and surrounding masonry, including how concealed defects will be handled.
- Perimeter sealing, insulation around the frames and internal making good.
- Decoration, with a clear description of the areas included.
- The applicable building regulations approval or certification route and who will arrange it.
- Lead times, the installation sequence, VAT and payment stages.
Distinguish included work from exclusions and provisional allowances. If repairs to concealed masonry cannot be priced until the old frames are removed, agree how that additional work will be recorded, priced and approved before it proceeds.
Agree manufacturing lead times and the delivery date before booking the installation team. Planning window delivery and installation together also allows for secure storage if the units arrive before fitting can begin. For occupied properties, agree access with residents and how each opening will be left secure and weatherproof during the work.
Planning consent and building regulations compliance are separate matters. Before signing, establish whether the installation can be certified through a relevant competent person scheme or needs another building control route. Keep the resulting documentation with the project records.
Record the handover and future maintenance
At handover, check every opening casement with the installer. It should operate without binding, close against its seals and lock as intended. Test any restrictors and ask for a demonstration of ventilators and other fittings. Record any adjustments or repairs still needed and agree when they will be completed.
Collect the final specification, guarantees, care instructions and relevant certificates. The owner or managing agent should receive straightforward operating instructions and know whom to contact if a fault develops. In a rental property, pass those instructions to the tenants too.
Include window checks in the property’s maintenance schedule, following the manufacturer’s instructions. Check the coatings, seals and hardware, and arrange any lubrication or adjustment as specified. Keep the agreed drawings and finish details so that a future contractor can identify the original specification when a component needs attention.