Temporary Roof Scaffolding on Commercial Refurbishments: What to Plan Before the Roof Comes Off

On a commercial refurbishment, the riskiest week is often the one when the old roof comes off. The building is open to the weather, the programme still has months to run, and in many cases tenants or stock are still inside.

A temporary roof scaffold keeps that week from becoming a problem. It covers the building so roofing, structural and internal trades can keep working whatever the forecast says. But it only works if it is planned before the strip-out starts, not ordered once the first storm is on the way.

This guide covers what contractors, project managers and building owners should settle before the roof comes off.

When a temporary roof makes sense

A temporary roof is worth considering whenever the permanent roof will be off, or partly off, for more than a short spell. On commercial refurbishments that usually means:

  • Full roof replacements on offices, retail units and warehouses
  • Structural repairs where the roof deck or frame has to be opened up
  • Restoration of older buildings with slow, careful roof work
  • Buildings that stay occupied, or hold stock or equipment, while work goes on
  • Projects where internal trades are booked to follow straight on

The question to ask is simple: what would a week of heavy rain do to this building and this programme? If the answer is water damage, lost trade days or an unhappy tenant, the temporary roof belongs in the plan from day one.

Start with the design, not the order

A temporary roof is not a standard scaffold with sheeting thrown over the top. It is a temporary structure in its own right, and it needs to be designed for the building it sits on.

The National Access and Scaffolding Confederation (NASC) publishes dedicated guidance for this work: TG9:18, Guide to the Design and Construction of Temporary Roofs and Buildings. Ask your scaffold contractor how their design is produced and checked, and get the drawings before work starts.

The design should answer at least these questions:

  • How wide is the span, and what supports the roof on each side?
  • What loads will the roof and scaffold carry, and where do they go?
  • How is the structure tied back, and what to?
  • Does the roof need to move, open or change as the work progresses?

Plan for wind, snow and rain

Once a scaffold is sheeted and roofed, it catches far more wind than an open frame. A temporary roof can also be lifted from below as well as pushed from the side. Wind and snow loads for these structures are assessed using the Eurocode for actions on structures, BS EN 1991.

In practice, that means the designer needs to know:

  • Where the site is, how exposed it is, and how tall the building is
  • Whether the sides will be fully sheeted or partly open
  • How long the roof will stay up, and through which months

A roof planned for a summer programme may not suit the same job if it overruns into winter. If the programme slips, go back to the designer before the season changes.

Check how it will tie to the building

Those extra loads have to go somewhere, and usually that means ties into the existing building. On a refurbishment, the building itself may be part of the problem: weak brickwork, old concrete, or a roof structure about to be removed.

Before the scaffold goes up, agree:

  • Which parts of the building can safely take tie loads
  • Whether anchors will be tested on site before they are relied on
  • What happens to the ties when walls, windows or cladding are being replaced
  • Whether freestanding or buttressed sections are needed where tying is not possible

This is also where the scaffold contractor and the structural engineer for the main works should talk directly, not through three layers of email.

Fire safety and occupied buildings

A temporary roof wraps the building in sheeting, so the sheeting has to be the right kind. For external use, look for flame-retardant sheeting certified to LPS 1215 or TS62. The NASC explains that these standards also cover temporary roof sheeting, and that the Joint Code of Practice on fire protection of construction sites links flame retardancy to insurance cover.

Note that “flame resistant” and “flame retardant” are not the same thing. Ask for the certificate, not just the product name.

If the building stays in use during the works, also plan:

  • Protected routes in and out for staff, tenants or the public
  • How fire escapes and alarm points stay usable under the scaffold
  • Security, so the scaffold does not become an easy way into the building

Rainwater, neighbours and the street

A temporary roof sheds a lot of water, and it has to land somewhere sensible. Plan where the run-off goes, so it does not pour onto a neighbour’s property, a footpath or the areas where deliveries are made.

On town-centre jobs, the footprint of the scaffold matters as much as its height:

  • If the scaffold or its base goes onto a public footway or road, a licence from the local highway authority is needed before it goes up
  • If the roof or scaffold oversails a neighbouring property, agree access with the owner early
  • Lighting, hoarding and pedestrian routes may need to be part of the arrangement

These approvals take time. Leaving them until the scaffold is booked is one of the most common ways a programme slips before work has even started.

Fit the roof to the programme

The temporary roof should follow the order of the works, not fight it. Map the sequence before installation:

  1. When the scaffold and roof go up, and how long that takes
  2. When the existing roof is stripped, and in what order
  3. Whether cranes, hoists or loading bays need access through or around the roof
  4. Whether the roof must be altered as new sections of permanent roof go on
  5. When it comes down, and what has to be finished before it does

On longer jobs, expect the arrangement to change. Good contractors plan for that from the start. For example, Alton Scaffolding’s temporary roof scaffolding is planned around the building and the sequence of works beneath it, and adapted as roofing and construction phases move on.

Inspections once it is up

Under the Work at Height Regulations 2005, a scaffold must be inspected after installation and before first use, at intervals of no more than seven days, and after any event likely to affect its stability. High winds are the obvious example for a sheeted, roofed structure.

Make sure it is clear who carries out those inspections, where the records are kept, and who on site can stop work if something looks wrong. After a storm, nobody should go back under the roof until it has been checked.

Checklist before the roof comes off

  • A temporary roof design, with drawings, for this building
  • Wind and snow loads assessed for the site and the season
  • Tie points agreed, and anchors tested where needed
  • Flame-retardant sheeting with certificates on file
  • Safe routes, fire escapes and security planned if the building is occupied
  • Rainwater run-off planned away from neighbours and footpaths
  • Highway licence and neighbour access agreed where needed
  • Installation, alterations and removal mapped against the programme
  • Inspection regime and records in place

Get these settled early, and the day the roof comes off becomes just another day on the programme.