What a CDM 2015 construction phase plan must actually contain

Every construction project in Great Britain needs a construction phase plan before work starts. Not the higher-risk ones, not the notifiable ones, all of them. Regulation 12 of the Construction (Design and Management) Regulations 2015 is explicit: the principal contractor must draw the plan up, and where there is only one contractor, that contractor prepares it. Despite that, the construction phase plan is still the document most likely to be a generic template with the project name changed at the top, and it is the one a CDM adviser, a client’s monitoring surveyor or an HSE inspector will ask for first. Here is what it has to contain to be worth the paper, and where the usual versions fall short.

It is required on every project, and it must be proportionate

The first misunderstanding is that a construction phase plan is only for big or notifiable jobs. It is not. The second is that proportionality means a small job can skip it. It cannot; proportionality means the plan should match the scale, complexity and risk of the work. A loft conversion does not need the plan a twenty-storey residential scheme needs, but it needs a plan. HSE’s guidance L153, the approved code of practice that sits behind CDM 2015, is clear that the effort should be focused on the risks that matter and not spent dressing up low-risk activities. A plan that runs to eighty pages of boilerplate and says nothing specific about the actual site is as non-compliant as no plan at all, because it does not do the one thing Regulation 12 asks of it: set out the health and safety arrangements for this project.

The three things it has to set out

Strip the templates away and Regulation 12, read with L153, asks the plan to cover three things. First, the management of the work: the health and safety aims for the project, the site induction and rules, the arrangements for cooperation and communication between the people on site, and the welfare facilities. Welfare is not optional and it is not something to arrive later; Schedule 2 of the regulations lists the toilets, washing, drinking water, rest and changing facilities that must be in place from the start of the construction phase. Second, the control of the specific risks on the site: what the significant risks are and the practical measures that control them, written for this job rather than copied from a library. Third, where the work involves any of the particular risks in Schedule 3, the specific measures for each.

Schedule 3 is the part templates get wrong

Schedule 3 lists the work that carries a particular risk and therefore needs specific attention in the plan: work that puts people at risk of burial in earthworks or sinking in ground, or of falling from height where the risk is particularly aggravated; work near high-voltage power lines; work with a risk of drowning; work in wells, underground earthworks and tunnels; work by divers; work in caissons or compressed air; work with explosives; and the assembly or dismantling of heavy prefabricated components. A generic template either ignores these or lists all of them with a tick, which tells the reader nothing. A plan that earns its keep names the Schedule 3 risks that actually apply to the site, and sets out the measure for each one, cross-referenced to the risk assessment and method statement that controls it. If a site has none of the Schedule 3 risks, say so; a short, honest statement is better than a page of irrelevant ones.

It is a live document, not a pre-start formality

The last failing is treating the plan as a thing produced once to get through the pre-start meeting and then filed. The construction phase plan has to be reviewed and revised as the work changes, because the risks change with it. New trades arrive, the sequence shifts, a design change introduces work that was not in the original scope. A plan that still describes the site as it was at week one, three months into the programme, is not evidence of a managed site; it is evidence that nobody has looked at it. Date the revisions, record what changed and why, and keep it where the people doing the work can actually read it.

What good looks like

A good construction phase plan is specific, proportionate and current. It describes this project, names the real risks and the measures that control them, puts welfare in place from day one, deals with the Schedule 3 work honestly, and is revised as the job moves. It does not need to be long. It needs to be true. The quickest test is to hand it to someone who has never seen the site and ask whether they could tell, from the plan alone, what is actually being built and what is being done to keep the people building it safe. If they cannot, the template has won and the plan has not started doing its job.

Reference

HSE, Managing health and safety in construction. Construction (Design and Management) Regulations 2015, Guidance on Regulations, L153. Available at https://www.google.com/url?q=https://www.hse.gov.uk/pubns/books/l153.htm&source=gmail&ust=1792657783832000&sa=E

About the author

Craig Collier is a chartered construction and quality professional (MCIOB, CQP MCQI, MAPM) and Director of StructAssure Ltd, which produces editable quality, health and safety documents for UK contractors. A free worked construction phase plan example and an editable template are available at https://www.google.com/url?q=http://www.structassure.co.uk/construction-phase-plan&source=gmail&ust=1792657783832000&sa=E, and a free worked inspection and test plan at https://www.google.com/url?q=http://www.structassure.co.uk&source=gmail&ust=1792657783832000&sa=E.